Kitchen fitting advice for Blackpool homes
How a kitchen is fitted: the order of work and who does what
If you have never had a kitchen fitted, the week ahead is a mystery. Who turns up first? When does the water go off? What is a first fix?
It is less of a muddle than it looks. The same jobs happen in the same order on nearly every kitchen. Know the order and you can plan round it.
Before anyone arrives
The kitchen is delivered, ideally a few days ahead and not weeks. You or the fitter check every box against the list. Anything missing is chased now.
You empty the cupboards and set up a camp kitchen somewhere else. A kettle, a microwave, a toaster and a bowl for washing up will do.
If a gas appliance is being taken out, the Gas Safe registered engineer is booked for the first morning or the day before.
Stage one: the old kitchen comes out
Water is turned off and the pipes capped. Electrical appliances are isolated. A gas hob or cooker is disconnected and the pipe capped by the gas engineer.
Then the worktops come up, the units come off the walls and the lot goes in the skip. Old tiles are chipped off if new ones are planned. By the afternoon you have a bare room and can see what you are dealing with.
Stage two: first fix
First fix means the hidden work that has to be in place before units cover the walls.
- The electrician runs cables for new sockets, the cooker, the extractor and any under-unit lights. Nothing is connected up yet.
- The plumber moves or extends the hot and cold feeds and the waste if the sink or washing machine is changing position.
- The gas engineer alters the gas pipe if the hob or cooker is moving.
- The plasterer patches or skims the walls. Fresh plaster needs time to dry before units go against it.
On a simple swap, with everything staying where it was, most of this stage is skipped. That is the main reason a like-for-like kitchen is so much quicker and cheaper.
Stage three: the fit
Now the kitchen fitter takes over, and this is the longest stretch. A UK cost guide allows four to eight days for the fitter on a typical kitchen.
- Flat-pack units are built
- A level line is set round the room
- Base units go in, starting from the corner, and are levelled and fixed
- Wall units and tall units are hung
- Worktops are cut, joined, sealed and fixed, with the sink and hob holes cut
- Doors, drawers and handles go on
- Plinths, end panels and cornice finish it off
If the worktop is stone, there is a gap here. The stone firm templates once the base units are fixed and comes back with the finished tops, often a week or more later. Ask for a temporary top so you can use the sink in the meantime.
Stage four: second fix and connections
- The plumber or fitter connects the sink, tap, dishwasher and washing machine and tests for leaks.
- The electrician fits socket fronts, wires in the oven, hob and extractor, tests the circuits and gives you a certificate for any new work.
- The gas engineer connects and tests a gas hob or cooker.
Then come the tiler, if there is a splashback, and whoever is painting. Flooring is fitted before or after the units depending on the type, so ask your fitter which he wants.
A UK cost guide puts the whole process at five to ten days for a typical kitchen.
Does the work need signing off?
Fitting units and worktops needs no approval from anyone. Some of the work around it does fall under the Building Regulations in England.
Gas work must be carried out by a Gas Safe registered engineer. New electrical circuits should be certified, and an electrician who belongs to a competent person scheme can certify their own work. If you are taking out a wall or changing a window or outside door, speak to building control at your council first. In Blackpool that is Blackpool Council.
Keep every certificate with the house papers. You will be asked for them when you sell.
Allowing for an older Blackpool house
The timings above are for an ordinary room. South Shore has terraced streets dating from the nineteenth century, and some of the bigger houses in town were once guest houses. In buildings like these, the rip-out is the stage that springs surprises: plaster that comes away with the tiles, pipes buried in odd places, a floor that turns out to slope.
Allow a day in hand. A good fitter will tell you on the first afternoon if he has found something that changes the plan or the price, before he carries on.
Ready to get a date? See kitchen fitting in Blackpool, or for a partial job, worktop fitting and replacement doors.
Common questions
How long does it take to fit a kitchen?
A UK cost guide gives four to eight days for the kitchen fitter's part and five to ten days overall once the electrician, plumber and other trades are counted. A straight swap is quicker. Stone worktops add a wait while they are made.
Should the floor be laid before the kitchen goes in?
That depends on the type of floor. Tiles are often laid first, right across the room. A floating floor such as laminate is usually laid afterwards, up to the legs, so it can expand. Your fitter will have a view, so ask before you book the flooring.
Can a kitchen fitter connect my cooker?
Not unless he holds the right registration. A gas cooker or hob must be connected by a Gas Safe registered engineer. An electric cooker or hob should be connected by a qualified electrician. Many fitters work alongside both and can arrange them for you.
Get your dates lined up
A kitchen fit depends on several people arriving in the right order. The fitter's start date is the peg the others hang on. Until you have it, the electrician, the plumber and the skip cannot be booked, and the kitchen waits in its boxes.
Say what is being fitted and where in Blackpool. You can ask without paying a penny.